Small Low Carbon Technologies (LCTs)

Over 60,000 customers request connections of LCTs to our distribution system. 80% of these are auto approved within minutes online. This includes solar PV and battery installations up to 5kW export capacity, electric vehicle chargers to 7kW and heat pumps to 10kW.
Over 60,000 customers request connections of LCTs to our distribution system. 80% of these are auto approved within minutes online. This includes solar PV and battery installations up to 5kW export capacity, electric vehicle chargers to 7kW and heat pumps to 10kW.
The vast majority of domestic and small commercial installations can be notified or requested online with approval provided while online.
96% of domestic and small commercial installations pass through our online portal with 80% auto-approved in Q4 2023 reducing lead times by up to 10 days.
The vast majority of domestic and small commercial installations can be notified or requested online with approval provided while online.
96% of domestic and small commercial installations pass through our online portal with 80% auto-approved in Q4 2023 reducing lead times by up to 10 days.

Our Smart Connect portal

We launched our LCT portal in 2021 which supports EV, battery, solar and heat pump applications. We have developed our technology to cater for multiple devices and larger solar applications (up to 50kW) to speed up the connection process. Where domestic customers do need work done at their house, this can be booked online and is free of charge.

Our Smart Connect portal

We launched our LCT portal in 2021 which supports EV, battery, solar and heat pump applications. We have developed our technology to cater for multiple devices and larger solar applications (up to 50kW) to speed up the connection process. Where domestic customers do need work done at their house, this can be booked online and is free of charge.

Meeting increasing demand

We saw a 200% increase in domestic multi-device applications in the past 12 months. We have increased auto-approval rates through applying robotic process automation (RPA) and training installers to use our digital tools to speed up their notifications. Our top three installers by volume submit 100% of their applications digitally.

Meeting increasing demand

We saw a 200% increase in domestic multi-device applications in the past 12 months. We have increased auto-approval rates through applying robotic process automation (RPA) and training installers to use our digital tools to speed up their notifications. Our top three installers by volume submit 100% of their applications digitally.

Outcomes

Completed 96% customer satisfaction for LCT supply upgrades - UK-leading

Completed 96% of domestic LCT applications now pass through our portal with 80% auto-approved in Q4 22/23, reducing lead time by up to 10 days, saving up to 511,820 days total since launch

Completed 15 FTE front-end processing resource avoided while handling seven times more application compared to 2021

Completed 10% increase in auto-approved rates between 21/22 and 22/23

Completed Reducing the time for fleet managers to assess electrification options from 25 days to under four hours when using our self-serve site planning tool - a 99% time saving