Installation of underground cables from Beddington to Addington

What are we doing?

We manage the electricity network delivering power to your area and connect and move power cables. Our engineers plan to upgrade the electricity network between Beddington Grid and Addington Grid in Croydon to maintain reliable electricity supplies for homes and businesses, manage increasing demand for electricity and support the drive to Net Zero.

What are we doing?

We manage the electricity network delivering power to your area and connect and move power cables. Our engineers plan to upgrade the electricity network between Beddington Grid and Addington Grid in Croydon to maintain reliable electricity supplies for homes and businesses, manage increasing demand for electricity and support the drive to Net Zero.

What will the work entail?

We are installing new electricity cables along a 6.5km route between the two substations. We are working closely with Croydon Borough Council to plan our work and minimise disruption. 

Our team will excavate trenches to lay pipework (ducts) along the route. We will then return to open excavations at intervals along the route to pull the new cables into position and connect them to our electricity network. 

We will start work in October 2025 and aim to complete the project by the end of 2026.

What will the work entail?

We are installing new electricity cables along a 6.5km route between the two substations. We are working closely with Croydon Borough Council to plan our work and minimise disruption. 

Our team will excavate trenches to lay pipework (ducts) along the route. We will then return to open excavations at intervals along the route to pull the new cables into position and connect them to our electricity network. 

We will start work in October 2025 and aim to complete the project by the end of 2026.

Will there be roadworks?

Work is due to take place in stages in the roads listed in the table below.

As well as using advance warning signs, we will write to residents, businesses and councillors with further details before work is due to start in each new area.

Safety is our priority and in consultation with the local highways authority, traffic management measures will be in place as we progress along the cable route.

Work will progress in stages, with traffic management and safety barriers being moved along the route in sequence with our working area.

We aim to complete the work as safely and as efficiently as possible to minimise the impact. We apologise for any inconvenience caused.

Will there be roadworks?

Work is due to take place in stages in the roads listed in the table below.

As well as using advance warning signs, we will write to residents, businesses and councillors with further details before work is due to start in each new area.

Safety is our priority and in consultation with the local highways authority, traffic management measures will be in place as we progress along the cable route.

Work will progress in stages, with traffic management and safety barriers being moved along the route in sequence with our working area.

We aim to complete the work as safely and as efficiently as possible to minimise the impact. We apologise for any inconvenience caused.

Road name Current status

Commerce Park

(From Beddington Substation to Mill Lane (near M&S)

IN PLANNING

Mill Lane

(From entry into Commerce Park to junction with Purley Way)

IN PLANNING

Waddon Road

(From junction with Purley Way to junction with Epsom Road)

WORK COMPLETE

Epsom Road

(From junction with Duppas Road to the junction with Waddon Road)

WORK COMPLETE

Duppas Road

(From Epsom Road to A232 Duppas Hill Road)

WORK COMPLETE

Duppas Hill Recreation Ground

(From Duppas Hill Road to Hillside Road)

Crossing Duppas Hill Road: Weekend working only (25-26 April and 2-3 May). Lane closure implemented during working hours.

Remainder: In planning.

Hillside Road

(From Cooper Road to Denning Avenue)

WORK COMPLETE

Denning Avenue

(From Hillside Road to Warham Road)

WORK COMPLETE

Warham Road

(From junction with Violet Lane to junction with Nottingham Road)

WORK PARTIALLY COMPLETE

Nottingham Road

(From Warham Road to A235 Brighton Road)

WORK COMPLETE

Bartlett Street

(From A235 Brighton Road to Selsdon Road)

18-24 April 2026
Lane closure around working area.
Give and take priority implemented.

Selsdon Road

(From junction with Bartlett Street to junction with Croham Road)

18-24 April 2026
Directional northbound closure of Selsdon Road from the Croham Arms Roundabout to Bartlett Street.
Signed diversion via St Peter's Road.
Bartlett Street remains accessible via Selsdon Road (southbound).

Croham Road

(From junction with Selsdon Road to start of Croham Valley Road)

27 April to 17 May 2026
Croham Road closed from South Park Hill Road to Croham Arms Roundabout.
Signed diversion in place via South Park Hill Road.
Access maintained for residents of Muggeridge Close and St Peter's Street.

Croham Valley Road

(From Manor Way working towards Addington Tower Substation)

WORK PARTIALLY COMPLETE