Installation of underground cables from Chatham to Wouldham

Resident information sessions

Thank you for attending our public information sessions on 3rd, 10th and 20th August.

Our next update session will be:

Date: Thursday 27 August
Time: 20:30 to 21:30
Venue: Borstal Village Hall, 1 Wouldham Road, Rochester, ME1 3JY

Resident information sessions

Thank you for attending our public information sessions on 3rd, 10th and 20th August.

Our next update session will be:

Date: Thursday 27 August
Time: 20:30 to 21:30
Venue: Borstal Village Hall, 1 Wouldham Road, Rochester, ME1 3JY

What are we doing?

We manage the electricity network delivering power to your area and connect and move power cables. Our engineers plan to upgrade the electricity network between our substations in Chatham and Wouldham to maintain reliable electricity supplies for homes and businesses, manage increasing demand for electricity and support the drive to Net Zero.

What are we doing?

We manage the electricity network delivering power to your area and connect and move power cables. Our engineers plan to upgrade the electricity network between our substations in Chatham and Wouldham to maintain reliable electricity supplies for homes and businesses, manage increasing demand for electricity and support the drive to Net Zero.

What will the work entail?

We are installing new electricity cables along a 6.5km route between the two substations. We are working closely with the local authorities to plan our work and minimise disruption. 

Our team will excavate trenches to lay pipework (ducts) along the route. We will then return to open excavations at intervals along the route to pull the new cables into position and connect them to our electricity network. 

We started work on 23 February 2026 and aim to complete the project by the end of end of 2027.

What will the work entail?

We are installing new electricity cables along a 6.5km route between the two substations. We are working closely with the local authorities to plan our work and minimise disruption. 

Our team will excavate trenches to lay pipework (ducts) along the route. We will then return to open excavations at intervals along the route to pull the new cables into position and connect them to our electricity network. 

We started work on 23 February 2026 and aim to complete the project by the end of end of 2027.

Will there be roadworks?

Work is due to take place in stages on the roads listed in the table below.

As well as using advance warning signs, we will write to residents, businesses and councillors with further details before work is due to start in each new area.

Safety is our priority and in consultation with the local highways authorities, traffic management measures will be in place as we progress along the cable route.

Work will progress in stages, with traffic management and safety barriers being moved along the route in sequence with our working area.

We aim to complete the work as safely and as efficiently as possible to minimise the impact. We apologise for any inconvenience caused.

Will there be roadworks?

Work is due to take place in stages on the roads listed in the table below.

As well as using advance warning signs, we will write to residents, businesses and councillors with further details before work is due to start in each new area.

Safety is our priority and in consultation with the local highways authorities, traffic management measures will be in place as we progress along the cable route.

Work will progress in stages, with traffic management and safety barriers being moved along the route in sequence with our working area.

We aim to complete the work as safely and as efficiently as possible to minimise the impact. We apologise for any inconvenience caused.

Road name Current status
School Lane
From Medway Grid Substation to Pilgrims Way

Next phase of work:
MID SEPTEMBER TO END OF OCTOBER 2026

Working from School Farm House west to substation.

Road closed at the point we are working.
Signed diversion in place via Wouldham Road.
Access maintained for properties.

View the letter we sent in August 2026

Pilgrims Way
From School Lane to Burham Road

Next phase of work:
24 AUGUST TO 14 SEPTEMBER 2026

Working from Ivy Cottage towards Bostal.

Road closed at the point we are working.
Access maintained for properties.

View the letter we sent in August 2026

Previous phases of work:

View the letter we sent in February 2026

Burham Road
From Pilgrims Way to Wouldham

Next phase of work: 
24 AUGUST TO 14 SEPTEMBER 2026

Working from Ivy Cottage towards Borstal.
Road closed at the point we are working.
Access maintained for properties.

View the letter we sent in August 2026

Future phase of work:
END OF OCTOBER TO END OF NOVEMBER 2026

Working from Nashenden Farm Lane to Ivy Cottage.
Three-way lights in place outside Nashenden Farm Lane.

View the letter we sent in August 2026

Previous phases of work:

View the letter we sent in February 2026

Wouldham Road
From Burham Road to Borstal Street

Dates of work:
27 JULY TO END OF AUGUST 2026

Traffic Management: Road closure
Next location: 2 Wouldham Road to 125 Borstal Street from the afternoon of Wednesday 26 August to Monday 31 August.
Signed diversions in place.
Access maintained for properties.

View the letter we sent in July 2026
View the letter we sent on 17th August 2026
View the letter we sent on 24th August 2026

Borstal Street
From Wouldham Road to Priestfields

Dates of work (up to Nashenden Lane):
MID AUGUST TO END OF AUGUST 2026

Traffic Management: Road closure
Next location: 2 Wouldham Road to 125 Borstal Street from the afternoon on Wednesday 26 August to Monday 31 August.
Signed diversions in place. 
Access maintained for properties.

View the letter we sent in July 2026
View the letter we sent on 17th August 2026
View the letter we sent on 24th August 2026

Priestfields
From Borstal Street to Maidstone Road
IN PLANNING
Maidstone Road
From Priestfields to Dale Road
IN PLANNING
Dale Road
From Maidstone Road to Jasper Avenue
IN PLANNING
Jasper Avenue
From Dale Road to St Williams Way
IN PLANNING
St Williams Way
From Jasper Avenue to Onslow Road
IN PLANNING
Onslow Road
From St Williams Way to Amherst Road
IN PLANNING
Amherst Road
From Onslow Road to Arthur Road
IN PLANNING
City Way
From Arthur Road to Old Pattens Lane
IN PLANNING
Old Pattens Lane
From City Way to Boundary Road
IN PLANNING
Boundary Road
From Old Pattens Way to West Chatham Primary Substation
IN PLANNING

Frequently asked questions