Installation of underground cables from Chessington to Kingston

What are we doing?

We manage the electricity network delivering power to your area and connect and move power cables. Our engineers plan to upgrade the electricity network between Chessington Grid and Kingston Grid to maintain reliable electricity supplies for homes and businesses, manage increasing demand for electricity and support the drive to Net Zero.

What are we doing?

We manage the electricity network delivering power to your area and connect and move power cables. Our engineers plan to upgrade the electricity network between Chessington Grid and Kingston Grid to maintain reliable electricity supplies for homes and businesses, manage increasing demand for electricity and support the drive to Net Zero.

What will the work entail?

We are installing new electricity cables along a 10km route between the two substations. We are working closely with the Royal Borough of Kingston and Transport for London to plan our work and minimise disruption. 

Our team will excavate trenches to lay pipework (ducts) along the route. We will then return to open excavations at intervals along the route to pull the new cables into position and connect them to our electricity network. 

We will start work in September 2025 and aim to complete the project by January 2027.

What will the work entail?

We are installing new electricity cables along a 10km route between the two substations. We are working closely with the Royal Borough of Kingston and Transport for London to plan our work and minimise disruption. 

Our team will excavate trenches to lay pipework (ducts) along the route. We will then return to open excavations at intervals along the route to pull the new cables into position and connect them to our electricity network. 

We will start work in September 2025 and aim to complete the project by January 2027.

Will there be roadworks?

Work is due to take place in stages in the roads listed in the table below.

As well as using advance warning signs, we will write to residents and councillors with further details before work is due to start in each new area.

Safety is our priority and in consultation with the local highways authorities, traffic management measures will be in place as we progress along the cable route.

Work will progress in stages, with traffic management and safety barriers being moved along the route in sequence with our working area.

We aim to complete the work as safely and as efficiently as possible to minimise the impact. We apologise for any inconvenience caused.

Will there be roadworks?

Work is due to take place in stages in the roads listed in the table below.

As well as using advance warning signs, we will write to residents and councillors with further details before work is due to start in each new area.

Safety is our priority and in consultation with the local highways authorities, traffic management measures will be in place as we progress along the cable route.

Work will progress in stages, with traffic management and safety barriers being moved along the route in sequence with our working area.

We aim to complete the work as safely and as efficiently as possible to minimise the impact. We apologise for any inconvenience caused.

Road name Current status
Fairoak Lane
(From Chessington substation, located on Fairoak Lane, to the junction of Leatherhead Road A243)

WORK COMPLETE

Leatherhead Road A243
(From junction of Fairoak Lane to Chessington Roundabout with Hook Road)

Current work: Harrow Close - Merritt Gardens
19 May to 19 June 2026

Temporary lights around the work space.
Merritt Gardens closed at junction with Leatherhead Road.
Signed diversion in place. 

Hook Road A243
(From junction of Leatherhead Road across Chessington Roundabout to Hook Road and Hook Junction Underpass)

12 June to 21 August
Lane closure around our works.

Hook Road Roundabout (over A3)

IN PLANNING

Hook Road A243
(From Hook Junction Underpass to junction of Ditton Road)

16 March - End of July 2026
Multi-way lights in place around the work space.

Ditton Road 
(From junction of Hook Road A243 to the junction of Ewell Road)
WORK COMPLETE
Ewell Road 
(From junction of Ditton Road to the junction of Lamberts Road)

12 January to end of June 2026
Two and three-way lights around our working area.

Lamberts Road 
(From junction of Ewell Road to progress along Villiers Avenue)
WORK COMPLETE
Villiers Avenue 
(From Lamberts Road to the roundabout with Lingfield Avenue and Grove Lane - known as Duke of Buckingham Roundabout)
WORK COMPLETE
Villiers Road
(From the roundabout with Lingfield Avenue and Grove Lane, to the junction of Fairfield and Hawks Road)

WORK COMPLETE

Hawks Road Crossing
(From the junction of Villiers Road to the junction of Albert Road)

WORK COMPLETE

Albert Road
(From the junction of Hawks Road to the junction of to London Road A308)

18 April to end of 12 June 2026

Road closed at the point we are working. Some parking spaces suspended.
Side streets made bi-directional to allow traffic to flow.

London Road A308 and A307
(From junction of Albert Road to junction of A307 Queen Elizabeth Road)
1 - 30 June 2026
Lane close around our working area
Queen Elizabeth Road
(From junction of A308 and A307 Queen Elizabeth Road to junction of Canbury Park Road)
18 May to 16 June 2026
Lane closed around our working area
Canbury Park Road
(From junction of Queen Elizabeth Road to junction of Richmond Road A307)

WORK COMPLETE

Richmond Road A307
(From junction of Canbury Park Road to junction of Sury Basin)

WORK COMPLETE

Henry Macaulay Avenue WORK COMPLETE
Sury Basin
(From Henry Macaulay Avenue, to the junction of A307 Richmond Road)
WORK COMPLETE

Frequently asked questions