Installation of underground cables from Chessington to Kingston

What are we doing?

We manage the electricity network delivering power to your area and connect and move power cables. Our engineers plan to upgrade the electricity network between Chessington Grid and Kingston Grid to maintain reliable electricity supplies for homes and businesses, manage increasing demand for electricity and support the drive to Net Zero.

What are we doing?

We manage the electricity network delivering power to your area and connect and move power cables. Our engineers plan to upgrade the electricity network between Chessington Grid and Kingston Grid to maintain reliable electricity supplies for homes and businesses, manage increasing demand for electricity and support the drive to Net Zero.

What will the work entail?

We are installing new electricity cables along a 10km route between the two substations. We are working closely with the Royal Borough of Kingston and Transport for London to plan our work and minimise disruption. 

Our team will excavate trenches to lay pipework (ducts) along the route. We will then return to open excavations at intervals along the route to pull the new cables into position and connect them to our electricity network. 

We will start work in September 2025 and aim to complete the project by January 2027.

What will the work entail?

We are installing new electricity cables along a 10km route between the two substations. We are working closely with the Royal Borough of Kingston and Transport for London to plan our work and minimise disruption. 

Our team will excavate trenches to lay pipework (ducts) along the route. We will then return to open excavations at intervals along the route to pull the new cables into position and connect them to our electricity network. 

We will start work in September 2025 and aim to complete the project by January 2027.

Will there be roadworks?

Work is due to take place in stages in the roads listed in the table below.

As well as using advance warning signs, we will write to residents and councillors with further details before work is due to start in each new area.

Safety is our priority and in consultation with the local highways authorities, traffic management measures will be in place as we progress along the cable route.

Work will progress in stages, with traffic management and safety barriers being moved along the route in sequence with our working area.

We aim to complete the work as safely and as efficiently as possible to minimise the impact. We apologise for any inconvenience caused.

Will there be roadworks?

Work is due to take place in stages in the roads listed in the table below.

As well as using advance warning signs, we will write to residents and councillors with further details before work is due to start in each new area.

Safety is our priority and in consultation with the local highways authorities, traffic management measures will be in place as we progress along the cable route.

Work will progress in stages, with traffic management and safety barriers being moved along the route in sequence with our working area.

We aim to complete the work as safely and as efficiently as possible to minimise the impact. We apologise for any inconvenience caused.

Road name Current status
Fairoak Lane
(From Chessington substation, located on Fairoak Lane, to the junction of Leatherhead Road A243)

WORK COMPLETE

Leatherhead Road A243
(From junction of Fairoak Lane to Chessington Roundabout with Hook Road)
From Fairoak Lane working towards Chessington World of Adventures.

19 November to 5 December 2025 (not including weekends) then from 5 January 2026.

Lane Closure with temporary lights around the work space.
Hook Road A243
(From junction of Leatherhead Road across Chessington Roundabout to Hook Road and Hook Junction Underpass)
IN PLANNING
Hook Road A243
(From Hook Junction Underpass to junction of Ditton Road)
IN PLANNING
Work planned for March to May 2026.
Ditton Road 
(From junction of Hook Road A243 to the junction of Ewell Road)
WORK COMPLETE
Ewell Road 
(From junction of Ditton Road to the junction of Lamberts Road)

12 January to end of May 2026

Two and three-way lights around our working area.
Lamberts Road 
(From junction of Ewell Road to progress along Villiers Avenue)
WORK IN PROGRESS

15 September to 12 February 2026.

Directional closure, southbound traffic.
Road closures at junctions where work crosses the junctions on Lamberts Road.
Traffic management will be removed over the Christmas period.
Villiers Avenue 
(From Lamberts Road to the roundabout with Lingfield Avenue and Grove Lane - known as Duke of Buckingham Roundabout)
WORK IN PROGRESS
15 September to 12 February 2026.

Directional closure, southbound traffic.
Road closures at junctions where Villiers Avenue crosses the following junctions:
Cheyne Hill
Eversley Road
Burney Avenue
King Charles Road

Traffic management will be removed over the Christmas period.
Villiers Road
(From the roundabout with Lingfield Avenue and Grove Lane, to the junction of Fairfield and Hawks Road)

12 January to end of April 2026.

Two, three and four-way lights around our working area.

Hawks Road Crossing
(From the junction of Villiers Road to the junction of Albert Road)

IN PLANNING

Work planned for April 2026.

Albert Road
(From the junction of Hawks Road to the junction of to London Road A308)
IN PLANNING

Work planned for May 2026.
London Road A308 and A307
(From junction of Albert Road to junction of A307 Queen Elizabeth Road)
IN PLANNING

Work planned for June 2026.
Queen Elizabeth Road
(From junction of A308 and A307 Queen Elizabeth Road to junction of Canbury Park Road)
IN PLANNING

Work planned for June to August 2026.
Canbury Park Road
(From junction of Queen Elizabeth Road to junction of Richmond Road A307)

Richmond Road - Elm Crescent: WORK COMPLETE

Elm Crescent - Outside Tempest House:
In planning

Outside Tempest House - Queen Elizabeth Road:
29 November to 17 December 2025.
Two-way traffic lights installed around our working area.
Richmond Road A307
(From junction of Canbury Park Road to junction of Sury Basin)
PLANNED:

7 February to 17 March 2026.

Multi-phase traffic lights around our working area. 
Side road closures.
Henry Macaulay Avenue WORK COMPLETE
Sury Basin
(From Henry Macaulay Avenue, to the junction of A307 Richmond Road)
WORK COMPLETE

Frequently asked questions