Installation of underground cables from Chessington to Kingston

Public Information Events

Date: Monday 22 June 2026
Time: 17:30 - 19:00
Venue: The North Star Pub, 271 Hook Road, KT9 1EQ

Dates: Monday 29 June
Time: 19:00 - 21:00
Venue: St Paul's Church Parish Hall, 224 Hook Road, KT9 1PL

Public Information Events

Date: Monday 22 June 2026
Time: 17:30 - 19:00
Venue: The North Star Pub, 271 Hook Road, KT9 1EQ

Dates: Monday 29 June
Time: 19:00 - 21:00
Venue: St Paul's Church Parish Hall, 224 Hook Road, KT9 1PL

What are we doing?

We manage the electricity network delivering power to your area and connect and move power cables. Our engineers plan to upgrade the electricity network between Chessington Grid and Kingston Grid to maintain reliable electricity supplies for homes and businesses, manage increasing demand for electricity and support the drive to Net Zero.

What are we doing?

We manage the electricity network delivering power to your area and connect and move power cables. Our engineers plan to upgrade the electricity network between Chessington Grid and Kingston Grid to maintain reliable electricity supplies for homes and businesses, manage increasing demand for electricity and support the drive to Net Zero.

What will the work entail?

We are installing new electricity cables along a 10km route between the two substations. We are working closely with the Royal Borough of Kingston and Transport for London to plan our work and minimise disruption. 

Our team will excavate trenches to lay pipework (ducts) along the route. We will then return to open excavations at intervals along the route to pull the new cables into position and connect them to our electricity network. 

We will start work in September 2025 and aim to complete the project by January 2027.

What will the work entail?

We are installing new electricity cables along a 10km route between the two substations. We are working closely with the Royal Borough of Kingston and Transport for London to plan our work and minimise disruption. 

Our team will excavate trenches to lay pipework (ducts) along the route. We will then return to open excavations at intervals along the route to pull the new cables into position and connect them to our electricity network. 

We will start work in September 2025 and aim to complete the project by January 2027.

Will there be roadworks?

Work is due to take place in stages in the roads listed in the table below.

As well as using advance warning signs, we will write to residents and councillors with further details before work is due to start in each new area.

Safety is our priority and in consultation with the local highways authorities, traffic management measures will be in place as we progress along the cable route.

Work will progress in stages, with traffic management and safety barriers being moved along the route in sequence with our working area.

We aim to complete the work as safely and as efficiently as possible to minimise the impact. We apologise for any inconvenience caused.

Will there be roadworks?

Work is due to take place in stages in the roads listed in the table below.

As well as using advance warning signs, we will write to residents and councillors with further details before work is due to start in each new area.

Safety is our priority and in consultation with the local highways authorities, traffic management measures will be in place as we progress along the cable route.

Work will progress in stages, with traffic management and safety barriers being moved along the route in sequence with our working area.

We aim to complete the work as safely and as efficiently as possible to minimise the impact. We apologise for any inconvenience caused.

Road name Current status
Fairoak Lane
(From Chessington substation, located on Fairoak Lane, to the junction of Leatherhead Road A243)

WORK COMPLETE

Leatherhead Road A243
(From junction of Fairoak Lane to Chessington Roundabout with Hook Road)

Works paused on Leatherhead Road while we complete the crossing of the Chessington Roundabout before the summer holidays.

Chessington Roundabout (Linking Leatherhead Road, Hook Road, Mansfield Road and Hook Road)

20 June to 1 July 2026
Mansfield Road closed at the Roundabout. Signed diversion in place via Coppard Gardens, Merritt Gardens and Leatherhead Road to the South, and Woodgate Avenue, Clayton Road and Hook Road to the North.

To allow traffic to flow safely, there will be some changes to access to side roads:

Ellingham Road will be closed at Leatherhead Road, with access via Bridge Road and Parbury Rise.
The South East slip road will be entry/exit via Bridge Road only.
The North East slip road will be entry/exit via Bridge Road only.
The South West slip road will be entry/exit via Mansfield Road only.
The North West slip road will remain as normal.

Hook Road A243
(From Chessington Roundabout to Roundabout over A3)

WORK PLANNED
21 July to end of October 2026
Works will start at the junction with Kelvin Grove, working southbound in sections and reaching the Chessington Roundabout by the end of October 2026.

Works will be in the central reservation, reducing the carriageway to one lane on either side.

Public information events:

Date: Monday 22 June 2026
Time: 17:30 - 19:00
Venue: The North Star Pub, 271 Hook Road, KT9 1EQ

Dates: Monday 29 June
Time: 19:00 - 21:00
Venue: St Paul's Church Parish Hall, 224 Hook Road, KT9 1PL

Hook Road Roundabout (over A3)

IN PLANNING

Hook Road A243
(From Hook Junction Underpass to junction of Ditton Road)

16 March to 21 July 2026
Multi-way lights around the works area.

Current location:
Verona Road

Our works will continue to Gladstone Road, where they will end on 21 July. Works will then move past the roundabout to Kelvin Grove (see two rows above).

Public information events:

Date: Monday 22 June 2026
Time: 17:30 - 19:00
Venue: The North Star Pub, 271 Hook Road, KT9 1EQ

Dates: Monday 29 June
Time: 19:00 - 21:00
Venue: St Paul's Church Parish Hall, 224 Hook Road, KT9 1PL

Ditton Road 
(From junction of Hook Road A243 to the junction of Ewell Road)
WORK COMPLETE
Ewell Road 
(From junction of Ditton Road to the junction of Lamberts Road)

Current location:
On bridge at Lamberts Road junction.
12 January to mid July 2026
Two and three-way lights around our working area.

Lamberts Road 
(From junction of Ewell Road to progress along Villiers Avenue)
WORK COMPLETE
Villiers Avenue 
(From Lamberts Road to the roundabout with Lingfield Avenue and Grove Lane - known as Duke of Buckingham Roundabout)
WORK COMPLETE
Villiers Road
(From the roundabout with Lingfield Avenue and Grove Lane, to the junction of Fairfield and Hawks Road)

WORK COMPLETE

Hawks Road Crossing
(From the junction of Villiers Road to the junction of Albert Road)

WORK COMPLETE

Albert Road
(From the junction of Hawks Road to the junction of to London Road A308)

WORK COMPLETE

London Road A308 and A307
(From junction of Albert Road to junction of A307 Queen Elizabeth Road)
WORK COMPLETE
Queen Elizabeth Road
(From junction of A308 and A307 Queen Elizabeth Road to junction of Canbury Park Road)
WORK COMPLETE
Canbury Park Road
(From junction of Queen Elizabeth Road to junction of Richmond Road A307)

WORK COMPLETE

Richmond Road A307
(From junction of Canbury Park Road to junction of Sury Basin)

WORK COMPLETE

Henry Macaulay Avenue WORK COMPLETE
Sury Basin
(From Henry Macaulay Avenue, to the junction of A307 Richmond Road)
WORK COMPLETE

 

Frequently asked questions