Assets and Operations

Constellation

Making substations smart by installing computers in them to analyse and reconfigure the network based on specific conditions to increase the resilience of the distribution network, free up capacity and allow more renewable generation to connect.

Key deliverables

  • Smart substation architecture, design and implementation
  • Site-to-site communication using a slice of the public 5G network

Target outcomes

  • Reduced curtailment for distributed energy resources (DER
  • Release network capacity for distributed generation connections- Increased ability to connect DER to the distribution network

Measures of success

  • Percentage reduction in curtailment of distributed energy resources (DER
  • Increased stakeholder satisfaction
  • Increased network utilisation
  • Improved network resilience

Stakeholder Engagement

As part of Constellation we carried out three engagement sessions with stakeholders from the wider industry to validate the smart substation solutions. We carried out workshops with

Technology developers in the energy and IT industry

Other Distribution Network Operators (DNO) in GB

Owners of Distributed Energy Resources (DER) The outputs from these sessions validated the need to enhance substations and make them smart

Timeline

Planned start:
01.05.2021
Target completion:
30.09.2026

Status

On Track

Milestones

  • Trials of the solutions at the power Networks Demonstration Centre (Dec 23)
  • Trials of the solutions in two UK power Networks areas (May 25)
  • Preparation for deployment into business as usual (Sep 26)
  • Project close down and reporting (Sep 26)

Change log

Featured projects

Customers

Our View

Enable customers reporting problems to initiate video calls with our customer service agents to facilitate faster resolution, reduce dispatch of engineers and improve safety.

Status: CompletedTarget end: 28.02.2025

See project
Assets and Operations

Smart Meter Data

Utilisation of data from smart meters to increase efficiency and accuracy of network operation and control, planning and asset management activities, and delivery of enhanced services to customers.

Status: CompletedTarget end: 15.11.2024

See project
Smart Networks

Flexibility Market Platform

An online platform facilitating the procurement and management of flexibility - from registration and qualification through to performance assessment and market settlement.

Status: In ProgressTarget end: 01.03.2026

See project
View all projects