Smart Networks

Satelline

Explore the costs and benefits of satellite technology as an alternative to LiDAR to demonstrate whether it can accurately measure vegetation proximity to UK Power Networks’ overhead lines.

Key deliverables

  • Assessment of the viability and benefits of satellite based vegetation scanning technology

Target outcomes

  • Reduced cost of vegetation scanning
  • Improved accuracy in vegetation measurement
  • Reduced CO2 emissions

Measures of success

  • Spend on vegetation scanning over 2 years
  • Reduction in vegetation-related CIs and CMLs
  • Avoidance of +200 tonnes CO2 emissions every two years

Stakeholder Engagement

We are actively working with the supply quality and vegetation management teams to understand challenges and pain points. We have engaged with other network operators to gather learnings from related projects and will share results of our findings on the viability of this technology, and get their input before scaling deployment

Timeline

Planned start:
01.09.2023
Target completion:
31.03.2024

Status

Completed

Milestones

  • Circuit selection and data imagery gathering complete (Nov 23)
  • Circuit selection and data imagery gathering complete (Nov 23)
  • Full scale implementation plan complete (Jan 24)
  • Pilot analytics and execution complete (Feb 24)
  • Final report (Mar 24)

Change log

Featured projects

Customers

Our View

Enable customers reporting problems to initiate video calls with our customer service agents to facilitate faster resolution, reduce dispatch of engineers and improve safety.

Status: CompletedTarget end: 28.02.2025

See project
Assets and Operations

Constellation

Making substations smart by installing computers in them to analyse and reconfigure the network based on specific conditions to increase the resilience of the distribution network, free up capacity and allow more renewable generation to connect.

Status: In ProgressTarget end: 30.09.2026

See project
Smart Networks

Flexibility Market Platform

An online platform facilitating the procurement and management of flexibility - from registration and qualification through to performance assessment and market settlement.

Status: CompletedTarget end: 01.03.2026

See project